A tub-to-shower conversion in Windsor costs $12,000–$22,000 and takes 5–10 days. The critical step is waterproofing behind the tile — we use a Schluter-Kerdi membrane system over a sloped pan, with a curbless option for aging-in-place accessibility.
The tub-to-shower conversion is the most common bathroom renovation in Windsor-Essex, and for good reason: an outdated acrylic tub surround eats floor space, looks tired, and becomes a safety hazard as homeowners age. Replacing it with a tiled walk-in or curbless shower transforms the room's function and value. The work hinges on one thing — waterproofing done right — and the difference between a shower that lasts thirty years and one that fails in three is entirely in the membrane system behind the tile. It's a core part of our full bathroom renovation in Windsor-Essex service.
| Tier | Budget | What's included |
|---|---|---|
| Standard walk-in shower | $12,000–$16,000 | Curb, ceramic tile, fiberglass pan, stock glass door |
| Mid-range tiled shower | $16,000–$19,000 | Upgraded tile, custom glass, niche + bench |
| Curbless barrier-free | $19,000–$22,000 | Linear drain, large-format porcelain, relocated drain |
The budget for a tub-to-shower conversion in Windsor runs $12,000–$22,000. The low end covers a standard walk-in shower with a curb, ceramic wall tile, a fiberglass pan replacement, and a stock glass door. The high end covers a curbless barrier-free shower with a linear drain, large-format porcelain wall tile, a custom glass enclosure, and a relocated drain. The biggest cost drivers are the drain move, the glass, and the tile selection.
Waterproofing is where we never compromise. We use a Schluter-Kerdi membrane system: a bonded waterproof sheet membrane applied over a sloped mortar pan, with preformed corners and a sealed curb. This is dramatically more reliable than the traditional cement-board-and-tar method, which relies on a hidden pan that can crack and leak for years before the damage shows. Every Kerdi installation is flood-tested before tile goes on — we fill the pan with water and watch the level for an hour. If it holds, we tile; if it doesn't, we fix it first.
| System | Reliability | Flood test | Typical lifespan |
|---|---|---|---|
| Schluter-Kerdi membrane | Excellent | Yes (1 hr) | 30+ years |
| Cement board + tar pan | Moderate | Rarely | 5–10 years before hidden leaks |
Moving the drain is the structural decision. A tub drain sits at one end of the alcove; a walk-in shower drain usually moves to the center or to a linear channel along the back wall. That means cutting the subfloor, relocating the PVC drain line, and re-pitching the pan. In Windsor's older homes with dimensional lumber joists, we sister in reinforcement where we cut. If the bathroom is on a concrete slab (common in some 1970s ranches), cutting the slab adds a day and $1,000–$1,500.
Curbless, or barrier-free, showers are worth the premium for homeowners planning to age in place. A curbless shower has no step at the entry — the floor pitches gently toward a linear drain, and the waterproofing extends past the curb line into the bathroom floor. This requires lowering the shower floor or raising the surrounding floor, so it's easiest in new construction or a full gut. The accessibility payoff is real: no trip hazard, wheelchair access, and a cleaner look. We build curbless showers to ADA-equivalent slopes (1/4 inch per foot, no more than 1/2 inch).
Custom glass is the long-lead item. Windsor-Essex glass fabricators run 2–3 weeks from template to install for a frameless enclosure. We order the glass the day the tile is set so it arrives as the grout cures — ordering after grout leaves the shower open and unusable for weeks. The glass is 3/8-inch tempered, with a door and a fixed panel, hardware in brushed nickel or matte black. Budget $2,500–$4,500 for the glass alone.
| Day | Work |
|---|---|
| Day 1 | Demolition, haul-away, tub removal |
| Day 2 | Rough-in plumbing, drain move, sister joists |
| Day 3 | Sloped pan + Kerdi membrane |
| Day 4 | Flood test & cure |
| Days 5–7 | Set wall & floor tile |
| Day 8 | Grout & seal |
| Days 9–10 | Fixtures, glass, final trim |
The day-by-day schedule for a standard tub-to-shower conversion: Day 1 demolition and haul-away, protect the floor, remove the tub; Day 2 rough-in plumbing, move the drain, sister joists if needed; Day 3 install the sloped pan and Kerdi membrane; Day 4 flood test and cure; Days 5–7 set wall and floor tile; Day 8 grout and seal; Days 9–10 install fixtures, glass, and final trim. The shower is fully usable the day the glass lands — typically 2–3 weeks after we started. We pair this with professional tile installation for showers and floors.
A well-built tub-to-shower conversion is one of the highest-satisfaction renovations we do. It adds daily comfort, improves safety, and returns strong value at resale. The key is treating waterproofing as the foundation, not an afterthought — because a leaking shower destroys the floor, the ceiling below, and the trust in the contractor who built it.
Local Windsor Tip
Custom glass shower enclosures are fabricated in Windsor-Essex with a 2–3 week lead time — order the glass the day the tile is set so it arrives as grout cures, instead of leaving the shower open for weeks.
Written by
James GreenwoodOwner & Founder · 20+ years experience
Founder and lead contractor of Limitless Homes & Construction Ltd with 20+ years of trade experience across Windsor-Essex. He coordinates every permit and inspection personally. Read full bio →
A tub-to-shower conversion in Windsor costs $12,000–$22,000, including demolition, waterproofing, tile, drain relocation, and a custom glass enclosure. Curbless or barrier-free layouts sit at the higher end.
We use a Schluter-Kerdi membrane system bonded to a sloped mortar pan, which is far more reliable than traditional cement board and tar. Every wet area is waterproofed before any tile is set.
A standard tub-to-shower conversion takes 5–10 days: demolition and rough-in on day 1–2, waterproofing and cure on day 3–4, tile and grout day 5–8, glass install after a 2–3 week fabrication lead time.
Get a free, no-obligation estimate from James Greenwood and the Limitless Homes team. Call 519-566-0436 or request a quote online.