Bathrooms, Curbless Showers & Tile

    Bathroom Remodel Timelines: From Day 1 Demolition to Final Grout

    August 30, 2026•6 min read•By James Greenwood
    Bathroom Remodel Timelines: From Day 1 Demolition to Final Grout

    A full bathroom renovation in Windsor takes 2–3 weeks: demolition and rough-in days 1–3, plumbing inspection day 4, waterproofing and cure days 5–7, tile days 8–12, grout and trim days 13–15. Water shutoffs are short, scheduled windows — not all-day outages.

    The most common question we hear before a bathroom renovation is simple: how long will I be without my bathroom? The honest answer for a full Windsor bathroom renovation is 2–3 weeks, but the experience is far less disruptive than that timeline suggests. Water shutoffs are short, scheduled windows, not all-day outages, and the noisiest, dustiest work is concentrated in the first three days. Here's the exact day-by-day schedule we follow so homeowners know what's happening and when. It's the schedule behind every complete bathroom renovation in Windsor-Essex we deliver.

    Windsor bathroom renovation — day by day

    Day(s)PhaseWater shutoff?
    Day 1Demolition & protection2–4 hrs
    Day 2Rough-in plumbingBrief
    Day 3Subfloor & framingNo
    Day 4Plumbing inspectionNo
    Days 5–6Waterproofing & cureNo
    Days 7–9Tile settingNo
    Day 10Grout & sealNo
    Days 11–12Fixtures & trim1–2 hrs
    Day 13Glass & punch-listNo

    Day 1 — Demolition and protection. We lay floor protection from the door to the bathroom, set up a HEPA air scrubber, and seal the work zone with zip walls. The toilet, vanity, tub or shower, and existing tile come out. A 2–4 hour water shutoff is needed to cap the supply lines. All debris is hauled away the same day. By evening the bathroom is down to the studs and subfloor.

    Day 2 — Rough-in plumbing. This is where Windsor's older homes often surprise us. Many pre-1980 homes have cast-iron or galvanized drain stacks that need replacing when a fixture moves, and undersized supply lines that get upgraded to PEX. We reroute the drain for a new shower base, move supply lines for a relocated vanity, and sister the floor joists where we've cut for the drain. Budget an extra day and $1,500–$3,000 if the stack needs replacing.

    Day 3 — Subfloor and framing. We level the subfloor over older joists (Windsor's humidity swings can leave subfloors cupped), repair any rot, and frame the shower curb and niche. If the layout changes a wall, this is when framing happens. Electrical rough-in for new lighting, a fan, and a heated floor (if included) runs the same day, filed with the ESA.

    Day 4 — Plumbing inspection. The City of Windsor plumbing inspector signs off on the drain and supply rough-in before any wall closes up. We schedule this inspection in advance so there's no waiting. Once it passes, we install the cement board or Schluter substrate.

    Days 5–6 — Waterproofing and cure. We install the Schluter-Kerdi membrane system over the sloped shower pan, seal every corner and curb, and flood-test the pan for an hour. A liquid membrane alternative needs 24–48 hours to fully cure before tile touches it. This cure time is non-negotiable — tiling over wet waterproofing traps moisture that fails the shower within a year.

    Days 7–9 — Tile setting. Shower walls first (so floor tile isn't damaged), then the floor. Large-format porcelain needs a flat substrate and a medium-bed mortar; mosaic floors need a tight grout joint. We center the layout, cut the field, and set every tile to a laser-leveled line. Grout happens after the thinset cures — usually day 10. Our tile installation for shower walls and floors covers every detail.

    Day 10 — Grout and seal. We grout the entire shower and floor, clean the haze, and apply a penetrating sealer to natural stone and porous tile. The sealer needs 24 hours before the shower gets wet.

    Days 11–12 — Fixtures and trim. The shower valve, showerhead, vanity, faucet, toilet, and accessories go in. A short water shutoff (1–2 hours) is needed to connect the vanity and toilet. Paint happens here too — bathroom-grade mold-resistant paint on walls and ceiling, part of our interior painting for bathroom walls and ceilings.

    Day 13 — Glass and final punch-list. The custom glass enclosure installs (if it wasn't ordered earlier), mirrors and hardware go up, and we walk the homeowner through a punch-list. The bathroom is fully functional by this point.

    The two things that extend this timeline are permit and inspection scheduling (we book inspections the day rough-in finishes so there's no gap) and custom glass lead time (2–3 weeks, ordered the day tile is set). For a primary-bathroom renovation where the family has a second bathroom, the disruption is minimal — the noisiest work is done in the first three days, and the rest is steady, contained progress. Knowing the schedule in advance is what makes a bathroom renovation livable, and that's exactly why we share it before we start.

    Local Windsor Tip

    Windsor's older homes often have undersized or cast-iron drain stacks that need replacing when you move the toilet — budget an extra day and $1,500–$3,000, and schedule the City plumbing inspection before the subfloor closes.

    Written by

    James Greenwood

    Owner & Founder · 20+ years experience

    Founder and lead contractor of Limitless Homes & Construction Ltd with 20+ years of trade experience across Windsor-Essex. He coordinates every permit and inspection personally. Read full bio →

    Frequently Asked Questions

    How long does a bathroom renovation take in Windsor?

    A full bathroom renovation in Windsor takes 2–3 weeks. Demolition and rough-in take 3 days, waterproofing needs 2 days to cure, tile takes 4–5 days, and grout and trim finish in 2–3 days.

    Will I be without water during my bathroom renovation?

    Water shutoffs are short, scheduled windows — usually 2–4 hours during demolition and fixture swap — not all-day outages. We coordinate shutoffs in advance and maintain access to a second bathroom.

    How long does shower waterproofing need to cure before tiling?

    A Schluter-Kerdi membrane bonds overnight, but a liquid waterproofing membrane needs 24–48 hours to fully cure before tile. We flood-test the pan before any tile is set.

    Planning a Windsor-Essex renovation?

    Get a free, no-obligation estimate from James Greenwood and the Limitless Homes team. Call 519-566-0436 or request a quote online.

    519-566-0436
    CallGallery